9 The Integration project is in charge of:
11 - Providing testing environment
12 - Supporting the use case teams
13 - Managing ONAP CI/CD chains
15 - Providing baseline images
16 - Validating the ONAP releases
18 The different activities may be summarized as follows (proportions are indicative):
24 - Management of daily/weekly CI chains
25 - Build baseline images
27 - Validate the release
29 For each release, the integration team provides the following artifacts:
31 - A daily CI chain corresponding to the release
32 - Staging labs to perform the pairwise testing (when not automated) and support
34 - Baseline Java and Python images
35 - oparent library to manage Java dependencies
36 - Test suites and tools to check the various ONAP components
37 - Use-case documentation and artifacts
38 - A testsuite docker included in the ONAP cluster to execute the robot based tests
39 - Configuration files (scripts, Heat templates, CSAR files) to help installing
41 - Wiki release follow-up tables (blocking points, docker versions,...)
43 Please see the `integration wiki page <https://wiki.onap.org/display/DW/Integration+Project>`_